News Flash

Posted on: September 17, 2020

2020 Clausen Avenue - Official East Lane Start Date (9/21/2020)

The contractor is officially scheduled to begin the east lane reconstruction on September 21, 2020, weather permitting. Residents on the east side of Clausen should have vehicles removed from your driveway by 7:00am on September 21st. The contractor will ...

Read on...

2020 Clausen Project - On-Street Parking Locations Road Construction Projects
Posted on: September 11, 2020

2021 Grand Avenue Improvements Project - First Public Meeting Recording

On September 9, 2020, the Village hosted a public meeting for residents of Grand Avenue (Linden Circle to Lawn Drive) to discuss the 2021 Grand Avenue Improvements project. The purpose of the meeting was to introduce improvements to the roadway and implem...

Read on...

Road Construction Projects
Posted on: September 11, 2020

2020 Clausen Avenue - Localized Water Service Interruption and Tentative East Lane Start Date

Phase I Progress and Localized Water Service Interruption 

The contractor is on schedule to complete all underground water and sewer infrastructure (Phase 1) work next week. On Monday, September 14th, the contractor is scheduled to make the final ...

Read on...

Road Construction Projects
Posted on: September 9, 2020

2021 Roadway Program - Grand Avenue Public Meeting on Improvements and Green Infrastructure

The Village identified Grand Avenue, Lawn Drive to Linden Circle, as a concrete reconstruction project for 2021. A public meeting for the proposed Improvements to Grand Avenue will be held via Zoom Webinar on Wednesday Evening, September 9, 2020 from 6pm ...

Read on...

Road Construction Projects
Posted on: September 4, 2020

2020 Prospect Avenue - West Lane Official Start Date (Updated 9/8/2020)

The contractor is officially scheduled to begin the removal of the west lane of Prospect Avenue on September 8, 2020, weather permitting. Residents with driveways on the west side of Prospect Avenue should have all vehicles removed by 7:00 am. Prospect St...

Read on...

2020 Prospect Avenue On-Street Parking Locations Road Construction Projects
Posted on: September 1, 2020

2020 Prospect Avenue - East Lane Open for Public Use

The contractor is scheduled to open the east lane for public use by the end of the work day, today. The concrete has cured to the proper strength and vehicles can not travel on the new pavement. Please be mindful that portions of the the Walnut Street int...

Read on...

Road Construction Projects
Posted on: September 1, 2020

2020 Clausen Avenue - Water Service Installations Today (No Planned Water Disruptions)

The contractor will begin working on water services today with no planned disruptions to service. They will be focusing primarily on homes with existing lead water services that have begun or completed replacing the remainder of their water services, priv...

Read on...

Road Construction Projects
Posted on: August 27, 2020

2020 Prospect Avenue - East Lane Completion and West Lane Estimated Start Date

The contractor is scheduled to complete the pouring of the east lane today. The concrete pavement will remain closed to public use while the curing process takes place. Curing is a process that allows concrete to build in strength, over time. The full cur...

Read on...

Road Construction Projects
Posted on: August 26, 2020

2020 Clausen Avenue - Water Service Connections Schedule

The contractor has completed of the installation of the new 8" water main. Pressure testing and chlorination of the water main are occurring this week per Illinois Environmental Protection Agency (IEPA) standards. The contractor is scheduled to begin...

Read on...

Lead in Drinking Water Road Construction Projects
Posted on: August 13, 2020

2020 Prospect Avenue - Construction Update 8/13/2020

The contractor is scheduled to pour the east side curb and gutter tomorrow, weather permitting. They will also begin pouring driveway aprons, which will continue into next week. The contractor will begin the removal of the east lane pavement immediately a...

Read on...

Road Construction Projects
Posted on: August 7, 2020

2020 Prospect Avenue - Confirmed East Lane Start Date (8/10/2020)

The contractor has confirmed that the removal of the east lane will occur on August 10, 2020. Please see the link below of the previous update with more information on on-street parking and the golf cart service. 

Read on...

2020 Prospect Update - August 4th, 2020 Road Construction Projects
Posted on: August 4, 2020

2020 Prospect Avenue - East Lane Start Date, On-Street Parking and Golf Cart Service

The contractor remains on schedule to begin the east lane reconstruction on August 10, 2020, weather permitting. Residents on the east side of Prospect should have vehicles removed from your driveway by 7:00am on August 10th. The contractor will begin the...

Read on...

Prospect Avenue On-Street Parking Locations Road Construction Projects
Posted on: July 29, 2020

2020 Clausen Avenue - Irrigation System Markings

All sprinkler heads located within the Village right-of-way should be marked by Monday, August 3rd. Please use marking paint or flags to mark sprinkler heads beginning 1’ behind the sidewalk on your side, and extending to the curb line. The Vill...

Read on...

Road Construction Projects
Posted on: July 27, 2020

2020 Clausen Avenue - Official Start Date is July 29, 2020

The contractor is scheduled to begin the 2020 Clausen Avenue Water Main and Roadway Improvement Program on July 29, 2020, weather permitting. The first phase of the project will include the installation of the 8" water main on the east side of the ro...

Read on...

Road Construction Projects