The Village has received an updated installation schedule from Layne-Christensen for the re-installation of the well #3 pipe.
Pump repairs for the well have been ongoing for the past several weeks. Reconstruction of the damaged bowl for the pump is expected to be completed during the middle of this week and epoxy coating of the well pipe should be completed by the end of this week.
The well rig and pump will be moved back on site the week of November 9th at which time work to clean the liner and televise the well will begin. Installation of the well pipe and testing of the pump will take place after that with the target completion date of November 13th.
Please note that unforeseen circumstances may result in timelines being shifted. Updated information will be posted when it is available.