The Contractor advised the Village they expect to be on site later this week to complete the remaining concrete work items. Work includes the 41st St and Harvey Ave intersection, the southwest corner of the 42nd St & Harvey intersection, and a pavement patch at 4226 Harvey. Please note we expect the intersection of 41st St and Harvey will be closed to all traffic starting Thursday. The closure will likely remain in place for at least a week.
Parkway restoration (topsoil and sod placement) and addressing any miscellaneous cleanup or touch up items is expected to begin towards the end of the month.