No work is expected next week. Parkway topsoil and sod placement will begin in September once cooler weather arrives. There are sections of concrete pavement that still need to be placed at the 42nd and 41st Street intersections. The Village is waiting for ComEd to relocate an underground duct and a power pole relocated at the 41st and Harvey intersection. Once relocation work on the duct is complete the Village intends to place concrete pavement at the 42nd Street and 41st Street intersections. We are anticipating this concrete work to occur in August and will provide a start date as soon as we are able.