Central Avenue Reconstruction

Posted on: June 23, 2023

Central Project update 6-23-23

Next week the contractor will continue working on the west side of Central Avenue preparing the roadway base. There may be delays on Central Avenue during working hours due to the construction equipment.

The contractor will have a second crew working on storm sewer and other utility adjustments at the Woodland and Elm intersection. A planned water outage for Woodland Avenue residents (47th to Burlington) is scheduled for Monday 6/26. A notice has been provided to impacted residents on Woodland. A copy of the notice can be downloaded at the following link:  Woodland Ave water outage notice

Residents should anticipate the intersection of Woodland and Elm will be blocked by construction equipment for the first couple days of next week.

Facebook Twitter Email

Other News in Central Avenue Reconstruction

Concrete pavement pour today (8/4)

Posted on: August 4, 2023

Central Avenue - Dust Control

Posted on: May 24, 2023

Project Update 3/31/2023

Posted on: March 31, 2023

Central Avenue Project Update 3/27/23

Posted on: March 27, 2023

Central Avenue Project Update 3/13/23

Posted on: March 13, 2023

Project update 1/11/2023

Posted on: January 11, 2023

Central Ave - unanticipated water outage

Posted on: November 21, 2022

Central Avenue Project Update 11/1/22

Posted on: November 1, 2022

Central Avenue Project Update 8/17/22

Posted on: August 17, 2022

Central Avenue Project Update 8/10/22

Posted on: August 10, 2022