This week the Contractor will continue to install storm sewer lateral pipes and inlet structures on Central Avenue. These storm sewers cross the roadway and convey the storm water from the street inlets to the new storm sewer main sewer located in the west parkway. Early next week we expect there will be a planned water outage for Central Ave residents between Burlington Ave and 47th Street in order to complete fire hydrant installation. A notice will be distributed to impacted residents prior to the outage.
We expect the contractor will begin working eastward on Elm Street with new sewer installation next week. The new storm sewer on Elm will run from Central Avenue to Lawn Avenue. We also expect roadway reconstruction of the west half of Central Avenue will begin later this month. We expect to provide more information on the first phase of the roadway reconstruction but the first phase will close the west half of the roadway so it can be reconstructed and one lane of northbound only traffic will be maintained on the east half of the road.