Harvey Avenue Reconstruction

Posted on: May 11, 2023

East side concrete work to begin 5/16, East side driveways to be closed

The contractor expects to begin concrete placement on the east side of Harvey Avenue on Tuesday, 5/16. All east side residents need to have their vehicles out of their driveways by 7am on 5/16. East side driveways will be closed 3-4 weeks. Please view the construction notice at the following link East Side Harvey Driveway Closure Notice 5-16 for additional information. A copy of this notice is expected to be hand delivered to each home today.