This week the Contractor is currently working on installing the sewer casing pipe under 47th Street (west of Commonwealth Drive). They are also installing new storm sewer on the north side of 47th Street heading east towards Central Avenue. We anticipate sewer work may begin on Central Avenue near 47th Street towards the end of this week or next week. The storm sewer installation work on Central will generally be located in the west parkway. Access to resident driveways will be maintained while this work progresses. The remaining tree removal work is expected to be completed this week or next. There are several smaller trees on the north side of 47th Street near the bottom of the roadway embankment to be removed and also clearing of an area of trees on the south side of 47th Street west of Commonwealth Drive for the storm sewer crossing.