Road Construction Projects

Posted on: July 2, 2020

2020 Motor Fuel Tax (MFT) Asphalt Resurfacing Project - Construction Update 7/2/2020

The contractor began removing and replacing curb/gutter, affected driveway aprons and sidewalks last week. They are scheduled to complete the remaining concrete work early next week. Next, they will begin adjusting all sewer structures in the area to allow for the grinding and resurfacing of the roadway. Residents removed from their driveways will regain access as soon as the concrete curing process is completed. Barricades will be removed from your driveway once you are allowed to use it again. The grinding and resurfacing of the roadway is tentatively scheduled to occur late next week or during the week of July 13th. 

Please contact Casey Biernacki at 708-246-1800 x 276 or at cbiernacki@wsprings.com with any questions or concerns.