Well 5 Construction

Posted on: May 7, 2020

[ARCHIVED] Well #5 Electrical Building and Pump Equipment Schedule

This spring the Village received "Notice to Proceed" approval from the IEPA for the final construction phase for the Well #5 project.

A pre-con meeting was held in March with the contractors for the project and the Village is currently in the material procurement stage, Construction work is anticipated to occur mid/late July and is expected to continue through August. 

Construction for the summer portion of the work should be confined to the Village’s ROW moving forward. Procurement of materials and dates are subject to change and may be impacted by material availability from the COVID-19 situation. Additional information, including specific construction dates are anticipated later this spring.

Preliminary Construction Schedule (Subject to change)

  • Preconstruction, Procurement and Submittals (March – June)
  • Construction (Late July – Early September)
  • Well Startup Commissioning (September – October)
  • Post-Construction Closeout (October – November)