Site security fencing was installed on Tuesday, July 16 and Layne-Christensen mobilized all drilling equipment to site.
Layne-Christensen will continue with rigging up of equipment and will begin mixing drilling mud and starting of the 30” borehole. Crews will work on a single shift basis until the upper casing is cemented in. After which, extended drilling operations will be anticipated following the installation of the surface casing.