Road Construction Projects

Posted on: September 4, 2018

2018 Roadway Program - Project Update

Lawn Avenue

The contractor has completed the pavement removals on the east side of Lawn Avenue this morning. They will begin removing curb/gutter, and a portion of the public sidewalk today. Please be advised that the east sidewalk may be closed for portions of the day as heavy machinery will be present. The contractor is leaving in a ~4 foot wide portion of the existing sidewalk to maintain pedestrian access to the east side of Lawn, which will be replaced once the street has been installed and reopened. 

Johnson Avenue

The contractor has begun saw cutting Johnson Avenue in preparation for pavement removals. At the current pace, the contractor is projected to begin pavement removals on Johnson Avenue around the middle of September. Please remember that this is an estimated start date. The contractor has been moving at an effective pace thus far, but weather/construction/unforeseen delays can always occur.  As Lawn Avenue progresses, a more detailed start date will be sent out. 


If you have any questions or concerns, please contact Casey Biernacki at 708-246-1800 x 276 or at cbiernacki@wsprings.com.

Facebook Twitter Google Plus Email